The Iraqi Megaproject No One Thought Would Happen Is Racing To Completion

The Iraqi Megaproject No One Thought Would Happen Is Racing To Completion

Progress on the key elements in TotalEnergies’ US$27 billion four-pronged project that will define Iraq’s oil and gas sector in the years to come ranges from 80% to 95% complete, according to reports from the country’s Oil Ministry. This runs from 80% finished on the rehabilitation work on the first Central Processing Facility — expected to double production capacity from 60,000 to 120,000 barrels per day (bpd) — to 95% finalised on the Artawi-PS1 export pipeline project. Overall, a senior source who works very closely with the Ministry exclusively told OilPrice.com over the weekend: “It [TotalEnergies] is doing exactly what it said it would, ahead of time in several respects, as it has been allowed to get on with the projects with almost none of the usual government interference.” He added: “If the rest of the work continues like this, then we are looking at potentially enormous gains in oil production in a relatively short time.”

Indeed it is, as the key element of TotalEnergies’ four-part plan — the Common Seawater Supply Project (CSSP), has long held out the promise that Iraq could finally deliver on its full hydrocarbons potential and become one of the world’s top three oil producers — second perhaps to the U.S. As analysed in full in my latest book on the new global oil market order, the CSSP involves taking and treating seawater from the Persian Gulf and then transporting it via pipelines to oil production facilities in order to maintain pressure in oil reservoirs, which will optimise the longevity and output of the fields. The basic plan for the CSSP is that it will be used initially to supply around six million bpd of water to at least five southern Basra fields and one in Maysan Province, and then extended for use in further fields. Both the longstanding stalwart Iraqi fields of Kirkuk and Rumaila – the former beginning production in the 1920s and the latter in the 1950s, with both having produced around 80% of the country’s cumulative oil production – require major ongoing water injection. The reservoir pressure at the former dropped significantly after output of only around 5% of the oil in place (OIP), while Rumaila produced more than 25% of its OIP before water injection was required, according to the International Energy Agency (IEA). This was because Rumaila’s main reservoir formation connects to a very large natural aquifer that has helped to push the oil out of the reservoir.

To reach and then sustain Iraq’s future crude oil production targets over any meaningful period, Iraq will have total water injection needs equating to around 2% of the combined average flows of the Tigris and Euphrates rivers or 6% of their combined flow during the low season, according to IEA figures. While withdrawals at these levels might look manageable, these water sources also have to continue to satisfy other end-use sectors, including the enormous agricultural sector. Informative in terms of the potential timeline for the completion of the CSSP is the case of Saudi Aramco’s Qurayyah Seawater Plant Expansion. The 2 million bpd expansion of an existing facility took nearly four years from the awarding of the front-end engineering, pro­curement and design contract – in May 2005 – to the time that water first began to flow in early 2009.

Source link